ConcreteFoundation package
Foundation in three days, slab the next
Footings, foundation walls and slab for a spec house at Durham Bridge — 40 m³ placed by a five-person crew, foundation formed and poured in three days and the slab in one.
ClientConfidential — reference on request
LocationDurham Bridge, NB
Our roleSubcontractor





The job
A cut-in lot in the woods, and a spec build where the whole concrete package had to clear the site inside a week.
- 01 — What was asked for
A builder needed the full concrete package for a spec house at Durham Bridge — footings, foundation walls and slab — on a wooded lot cut in for the build.
- 02 — What we did
A five-person crew placed 40 m³ in total. Footings and walls were formed, poured and stripped over three days; the slab followed as a single one-day pour.
- Foundation formed, poured and stripped in three days
- Slab placed and finished in one
- Five-person crew on the whole package
- 03 — How it finished
Complete in May 2025, four working days from footings to finished slab.