Concrete province-wide across New Brunswick · Framing within 45 minutes of Fredericton
WorkSafeNB registered506 206 9636
JACE CONSTRUCTIONCONCRETE + FRAMING
ConcreteFoundations & footings

Shop foundation and footings in two weeks

Footings and five-foot foundation walls for a 7,200 sq ft ServiceMaster shop — 48 m³ total with a 35 m³ single pour, done by a five-person crew in two weeks.

ClientServiceMaster
LocationNew Brunswick
Our roleSubcontractor
Formed foundation wall running the length of the ServiceMaster shop footprint with rebar in place
Poured foundation wall corner with the forms stripped
Tied rebar cages for the column pads before placement
Wall forms set in the trench with rebar tied through

Formed foundation wall running the length of the ServiceMaster shop footprint with rebar in place

01 / 04
The job

A two-week window for the whole structural concrete scope, with the largest placement — 35 m³ of the 48 — going in as one pour.

  1. 01 — What was asked for

    A 7,200 square foot ServiceMaster shop needed its structural concrete: footings, five-foot foundation walls and the column pads for the building frame.

  2. 02 — What we did

    A five-person crew formed and placed 48 m³ of 25 MPa concrete over two weeks. The main wall run went in as a single 35 m³ placement rather than being broken into sections, with column pads formed and tied alongside.

    • 35 m³ of the 48 placed in one continuous pour
    • Five-person crew across the full scope
    • Footings, five-foot walls and column pads inside two weeks
  3. 03 — How it finished

    Foundation and footings complete mid-July 2026, two weeks from start.

Pricing a job?

Send the drawings, the scope and a bid date

We’ll route it straight to the right division and come back with a number.

Invite JACE to Bid